You’re putting together a budget for project that will run over the course of the year. Show how your spending will change over the course of the year. If you don’t have a project in mind, then go with this one:
Your project is to design and deliver powerpoint training for a large, nationally dispersed organisation.
Acceptance criteria
Use a spreadsheet with the following layout. I’ve prepopulated with some typical high-level project phases:
Cost item
Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec
Phase 1: Discovery
Item A
Item B
Phase 2: Design
Phase 3: Delivery
Total costs
£–
£–
£–
£–
£–
£–
£–
£–
£–
£–
£–
£–
Set the currency of the estimates to match your local currency.
Resources
A fixed cost is one that will not change regardless of any other variables (such as the number of people, or the size of the files to be stored).
You’re putting together a budget for project that will run over the course of the year. Show how your spending will change over the course of the year. If you don’t have a project in mind, then go with this one:
Your project is to design and deliver powerpoint training for a large, nationally dispersed organisation.
Acceptance criteria
Use a spreadsheet with the following layout. I’ve prepopulated with some typical high-level project phases:
Cost item
Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec
Phase 1: Discovery
Item A
Item B
Phase 2: Design
Phase 3: Delivery
Total costs
£–
£–
£–
£–
£–
£–
£–
£–
£–
£–
£–
£–
Set the currency of the estimates to match your local currency.
Resources
A fixed cost is one that will not change regardless of any other variables (such as the number of people, or the size of the files to be stored).
You’re putting together a budget for project that will run over the course of the year. Show how your spending will change over the course of the year. If you don’t have a project in mind, then go with this one:
Your project is to design and deliver powerpoint training for a large, nationally dispersed organisation.
Acceptance criteria
Use a spreadsheet with the following layout. I’ve prepopulated with some typical high-level project phases:
Cost item
Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec
Phase 1: Discovery
Item A
Item B
Phase 2: Design
Phase 3: Delivery
Total costs
£–
£–
£–
£–
£–
£–
£–
£–
£–
£–
£–
£–
Set the currency of the estimates to match your local currency.
Resources
A fixed cost is one that will not change regardless of any other variables (such as the number of people, or the size of the files to be stored).